8. Upgrade of P-3 mission systems for the Air Force

9. Acquisition of a light armoured vehicle for the Army

10. Replacement of Boeing 727 aircraft for the Air Force

11. Replacement or upgrade of tactical communications for the Army

12. ANZAC Ships

Annual Report for the year ended 30 June 2005

Contents | Previous | Next

Part 3: Departmental financial statements (continued)

Output Class - Management of equipment procurement

8. Upgrade of P-3 mission systems for the Air Force

This project will upgrade the sensors and mission management systems required for the Royal New Zealand Air Force P-3 Orion maritime patrol aircraft to conduct surface surveillance tasks.

Target
Delivered
  • The intention is to complete the evaluation of the Best and Final Offer from the preferred tenderer by 31 July 2004, and following consultation, make recommendations to the Government in the negotiating and awarding of a contract.
  • A contract was signed with L3 Communications Integrated Systems on 5 October 2004.
  • Preliminary Design Reviews for the Mission Planning System and Group B equipment were completed in May and June 2005.
  • Some early system installations began on the first aircraft at Safe Air, Woodbourne in June 2005. This aircraft is due for acceptance in August 2005.
Financial summary of pre-acquisition costs charged to departmental output class - Management of equipment procurement in 2004/05 (GST exclusive)
 
$
 
Budget for pre-acquisition costs 163,172  
Expenditure to 30 June 2005 163,172  
Financial summary of project costs charged to non-departmental appropriations as at 30 June 2005 (GST inclusive)
 
$
 
Project approval 373,069,314  
Foreign exchange variances to date and forecast to complete (26,024,279)  
GST 46,633,667  
Total approved cost 393,678,702  
GST exclusive    
Expenditure to 30 June 2004 -  
Expenditure 2004/05 65,617,789  
Future commitments and forecasts 280,869,126  
  346,486,915  
GST    
GST to 30 June 2004 -  
Expenditure 2004/05 325,148  
Future commitments and forecasts 46,441,712  
  46,766,860  
Total forecast cost to complete 393,253,775  
9. Acquisition of a light armoured vehicle for the Army

These Army vehicles are intended to provide protected mobility for light infantry manoeuvre groups in combat or when undertaking peace support operations.

Target
Delivered
  • The project milestones in 2004/05 are to:
    • complete delivery of the light armoured vehicles and special tools and test equipment by November 2004
    • accept the final vehicles by January 2005
    • close the project by June 2005.
  • 104 vehicles were in service with the New Zealand Army at 31 December 2004.
  • 99% of spares and special tools were delivered at 30 June 2005.
  • A delay in deciding armour requirements will extend the closure date of this project to June 2006.
Financial summary of project costs charged to non-departmental appropriations as at 30 June 2005 (GST inclusive)
 
$
 
Project approval 580,296,353  
Foreign exchange variances to date and forecast to complete 14,703,406  
GST 72,537,044  
Total approved cost 667,536,803  
GST exclusive    
Expenditure to 30 June 2004 563,503,741  
Expenditure 2004/05 21,520,539  
Future commitments and forecasts 9,231,262  
  594,255,542  
GST    
GST to 30 June 2004 45,071,115  
Expenditure 2004/05 7,167,154  
Future commitments and forecasts 52,631  
  52,290,900  
Total forecast cost to complete 646,546,442  
10. Replacement of Boeing 727 aircraft for the Air Force

This project replaces the Boeing 727 aircraft with Boeing 757 aircraft to provide greater range and payload capacity.

Two aircraft have been purchased. The intention is to modify them to provide a dual passenger/freight capability.

Target
Delivered
  • In 2004/05 it is planned to:
    • commence negotiations with identified suppliers to undertake the conversion.
    • enter into contracts and commence the conversion.
  • The modifications required to provide a combined passenger/freight capability were finalised in July 2004.
  • Mobile Aerospace Engineering and Boeing are approved as the preferred tenderers.
  • Due to the complexity of the programme the documentation took six months to finalise and was released to industry for final costing on 1 April 2005. Industry responded in late April. Final Cabinet approval for the conversion was being sought at 30 June 2005.
  • A revised start date for the modification programme is June 2006.
  • Subsequent to 30 June 2005 Cabinet approval was given to additional funding of $45.675 million to meet the modification programme without making major tradeoffs. The increase in cost is due to an increased need for engineering analysis; additional costs for certification, data licences and documentation; inflation and foreign exchange movement.
Financial summary of project costs charged to non-departmental appropriations as at 30 June 2005 (GST inclusive) including approval for additional funding
 
$
 
Project approval 220,603,000  
Foreign exchange variances to date and forecast to complete (12,623,885)  
GST 27,575,000  
Total approved cost 235,554,115  
GST exclusive    
Expenditure to 30 June 2004 108,233,771  
Expenditure 2004/05 236,460  
Future commitments and forecasts 99,365,445  
  207,835,676  
GST    
GST to 30 June 2004 13,048,133  
Expenditure 2004/05 6,959  
Future commitments and forecasts 14,520,002  
  27,575,094  
Total forecast cost to complete 235,410,770  
11. Replacement or upgrade of tactical communications for the Army

This project replaces and/or upgrades existing Army short range communications systems to provide high band width (higher capacity) digital theatre communication systems to support command and control requirements of the New Zealand Defence Force Battalion Group operations.

Target
Delivered
  • The final delivery of radios is expected by September 2004. Ancillary equipment is expected to be complete by March 2005.
  • The delivery of radios is complete.
  • Ancillary equipment is still being purchased. Delays in supply and obtaining export licenses will extend the expected completion date to December 2005.
Financial summary of project costs charged to non-departmental appropriations as at 30 June 2005 (GST inclusive)
 
$
 
Project approval 119,223,000  
Foreign exchange variances to date and forecast to complete 4,786,625  
GST 14,903,000  
Total approved cost 138,912,625  
GST exclusive    
Expenditure to 30 June 2004 118,801,182  
Expenditure 2004/05 1,560,436  
Future commitments and forecasts 3,456,544  
  123,818,162  
GST    
GST to 30 June 2004 11,205,187  
Expenditure 2004/05 304,275  
Future commitments and forecasts 3,386,452  
  14,895,914  
Total forecast cost to complete 138,714,076  
12. ANZAC Ships

This project is to procure two ANZAC class frigates from the 10-ship build programme, to replace two existing surface combatants complete with spares and training facilities.
New Zealand ships, HMNZS Te Kaha and HMNZS Te Mana have been delivered and are in service.

Target
Delivered
  • In 2004/05 it is planned to discontinue New Zealand's involvement in this project and settle any outstanding obligations.
  • The Ministry has requested the Australian Department of Defence to identify final Treaty obligations with a view to settlement by 30 June 2006.
  • There are no other matters to report.
Financial summary of project costs charged to non-departmental appropriations as at 30 June 2005 (GST inclusive)
 
$
 
Approved contract at base rates
938,949,321  
Approved escalations at base rates 252,391,118  
Foreign exchange variances to date and forecast to complete
125,151,984  
GST 153,808,491  
Total approved cost 1,470,300,914  
GST exclusive    
Expenditure to 30 June 2004 1,241,795,590  
Expenditure 2004/05 840,089  
Future commitments and forecasts 500,000  
  1,243,135,679  
GST    
GST to 30 June 2004 157,476,992  
Expenditure 2004/05 1,589  
Future commitments and forecasts -  
  157,478,581  
Total forecast cost to complete 1,400,614,260  

Top | Previous | Next