Reports and Publications

Within this section

Output Class - Management of equipment procurement (continued)

1. Acquisition of new maritime forces vessels

2. Acquisition of medium range anti armour weapon

3. Acquisition of direct fire support weapon (area)

4. Upgrade and refurbishment of C-130H aircraft

5. Upgrade of P-3K Orion mission systems

6. Replacement of Boeing 727 aircraft

Annual Report for the year ended 30 June 2006

Contents | Previous | Next

Part 3: Departmental financial statements (continued)

Output Class - Management of equipment procurement

It will continue management of the following projects:

1. Acquisition of new maritime forces vessels for the Royal New Zealand Navy

This project is for the acquisition of a multi role vessel (MRV), two offshore patrol vessels (OPV) and four inshore patrol vessels (IPV) to meet inshore and offshore requirements for maritime surface surveillance in New Zealand's Exclusive Economic Zone in the South Pacific. The multi role vessel, in addition to carrying out patrol duties, will provide tactical sealift for the New Zealand Defence Force, support disaster relief and peace support operations, provide diplomatic and military presence, and provide training. The vessels are forecast to enter service by 2008.

Target
Delivered
  • The project milestones in 2005/06 are to:
    • complete all design activity on all three vessel types
  • Detailed design reviews have been held in accordance with the programme. All reviews have been completed other than the final review of the MRV and Ship to Shore Transfer which will be conducted after the MRV arrives in Melbourne.
  • progress the MRV build from initial keel lay to launch in preparation for fit out
  • The MRV (to be named HMNZS Canterbury), was launched on 11 February 2006, and is scheduled to undertake sea trials in July 2006 and depart Rotterdam for Melbourne in August 2006. Fit out of the gun and military communications, along with crew training, will occur between October and December 2006. Delivery of the MRV is planned for January 2007. Both Landing Craft (LCMs) were launched in April, completed sea trials in May and will be embarked in the MRV for delivery in Melbourne in October 2006.
  • commence the build of both OPVs
  • The keel lay of OPV1 (to be named HMNZS Otago) occurred on 16 December 2005 with launch scheduled for 18 November 2006. At 30 June 2006, construction of OPV1 was approximately 50% complete and OPV2 (to be named HMNZS Wellington) about 10% complete. Six modules for OPV2 are being constructed in the Netherlands for transport to Melbourne on the MRV.
  • commence the build of the first two IPVs.
  • Keel lay for IPV1 (to be named HMNZS Rotoiti ) occurred on 10 March 2006. At 30 June 2006, construction of IPV1 was 40% complete with launch scheduled for January 2007. IPV2 (to be named HMNZS Hāwea ) was 10% complete and steel had been cut for IPV3 (to be named HMNZS Pūkaki ). All IPVs are scheduled for delivery in 2007 with IPV4 (to be named HMNZS Taupō ) expected in December 2007.
Financial summary of project costs charged to non-departmental appropriations as at 30 June 2006 (GST inclusive)
 
$
 
Project approval 499,724,161  
Foreign exchange variances to date and forecast to complete (3,358,032)  
GST 62,466,000  
Total approved cost 558,832,129  
GST exclusive    
Expenditure to 30 June 2005 114,034,511  
Expenditure 2005/06 152,024,097  
Future commitments and forecasts 230,306,265  
  496,364,873  
GST    
GST to 30 June 2005 1,976,000  
Expenditure 2005/06 4,475,836  
Future commitments and forecasts 56,014,162  
  62,465,998  
Total forecast cost to complete 558,830,871  
  Approval Rate Forecast Average Rate
AUD 0.8821 0.8979
CAD 0.8210 0.8471
EUR 0.5059 0.5085
GBP 0.3464 0.3455
JPY 65.5436 70.9001
NOK 4.2444 4.3357
SEK 4.6683 4.8496
USD 0.6215 0.6496
AUD 0.8965
CAD 0.8339
EUR 0.4906
GBP 0.3444
JPY 70.9000
NOK 4.2192
SEK 4.8496
USD 0.6477
2. Acquisition of medium range anti-armour weapon for the New Zealand Army

This weapon will provide land forces with a medium range capability against armoured vehicles and other targets.

Target
Delivered
  • Deliveries are scheduled to be completed in the second half of 2006.
  • On-going technical support being negotiated.
  • The Javelin system was delivered in June 2006, except for the missiles. The missile delivery date will be advised by the United States Government in September 2006.
Financial summary of project costs charged to non-departmental appropriations as at 30 June 2006 (GST inclusive)
 
$
 
Project approval 23,856,000  
Foreign exchange variances to date and forecast to complete (2,019,747)  
GST 2,982,000  
Total approved cost 24,818,253  
GST exclusive    
Expenditure to 30 June 2005 11,220,443  
Expenditure 2005/06 5,248,473  
Future commitments and forecasts 5,367,337  
  21,836,253  
GST    
GST to 30 June 2005 125  
Expenditure 2005/06 838,185  
Future commitments and forecasts 2,143,690  
  2,982,000  
Total forecast cost to complete 24,818,253  
3. Acquisition of very low level air defence system for the New Zealand Army

This project will purchase an alerting and cueing system to bring the Army's Mistral air defence system up to an improved operational standard.

Target
Delivered
  • Deliveries are scheduled to be completed in the second half of 2006.
  • Transport aircraft availability and small schedule slippage will see delivery being achieved in October 2006.
Financial summary of project costs charged to non-departmental appropriations as at 30 June 2006 (GST inclusive)
 
$
 
Project approval 13,728,376  
Foreign exchange variances to date and forecast to complete 490,511  
GST 1,716,047  
Total approved cost 15,934,934  
GST exclusive    
Expenditure to 30 June 2005 3,768,237  
Expenditure 2005/06 3,402,285  
Future commitments and forecasts 7,048,365  
  14,218,887  
GST    
GST to 30 June 2005 8,729  
Expenditure 2005/06 4,259  
Future commitments and forecasts 1,703,058  
  1,716,046  
Total forecast cost to complete 15,934,933  
4. Upgrade and refurbishment of C-130H aircraft for the Royal New Zealand Air Force

This project will extend the life of the Royal New Zealand Air Force C-130H Hercules aircraft by upgrading the aircraft systems and undertaking some structural refurbishment work.

The first aircraft will be completed in 2007 with the final aircraft completed in 2010.

Target
Delivered
  • The project milestones in 2005/06 are to:
    • complete all design activity for aircraft upgrade
    • commence work on the modification of the prototype aircraft.
  • The majority of the design effort has been completed.
  • The induction of aircraft number one into the upgrade and refurbishment programme achieved in October 2005.
  • Work is progressing as planned on the removal of redundant systems and structural components requiring replacement.
  • The contractor is now receiving parts and equipment into store as planned.
Financial summary of project costs charged to non-departmental appropriations as at 30 June 2006 (GST inclusive)
 
$
 
Project approval 233,739,000  
Foreign exchange variances to date and forecast to complete (1,582,072)  
GST 29,217,000  
Total approved cost 261,373,928  
GST exclusive    
Expenditure to 30 June 2005 43,962,237  
Expenditure 2005/06 65,889,248  
Future commitments and forecasts 121,631,500  
  231,482,985  
GST    
GST to 30 June 2005 6,100  
Expenditure 2005/06 104,075  
Future commitments and forecasts 29,106,825  
  29,217,000  
Total forecast cost to complete 260,699,985  
5. Upgrade of P-3K Orion mission systems for the Royal New Zealand Air Force

This project will upgrade the sensors and mission management systems required for the Royal New Zealand Air Force's P-3K Orion maritime patrol aircraft to conduct surface surveillance tasks.

The first aircraft will be completed in 2008 with the final aircraft completed in 2010.

Target
Delivered
  • The project milestones in 2005/06 are to:
    • complete an interim installation of the electro-optics system on three aircraft
    • commence work on the full modification for the first aircraft in Greenville, Texas
    • complete all detailed design work for the upgrade.
  • Installation of interim electro-optics on the three aircraft, which were being fitted with the system, has been completed.
  • Design reviews for the main upgrade equipment suite, structural design and software has been essentially completed.
  • Prototype aircraft positioned with contractor in the United States and removal of redundant systems underway.
  • Contractor now receiving parts and equipment into store.
Financial summary of project costs charged to non-departmental appropriations as at 30 June 2006 (GST inclusive)
 
$
 
Project approval 373,069,314  
Foreign exchange variances to date and forecast to complete (25,739,590)  
GST 46,633,667  
Total approved cost 393,963,391  
GST exclusive    
Expenditure to 30 June 2005 65,617,789  
Expenditure 2005/06 110,719,174  
Future commitments and forecasts 170,908,326  
  347,245,289  
GST    
GST to 30 June 2005 325,148  
Expenditure 2005/06 892,358  
Future commitments and forecasts 45,416,145  
  46,633,651  
Total forecast cost to complete 393,878,940  
6. Boeing 757 Acquisition/Modification for the Royal New Zealand Air Force

This project replaces the Boeing 727 aircraft with Boeing 757 aircraft to provide greater range and payload capacity.

Two aircraft have been purchased and are being operated by the Royal New Zealand Air Force in a passenger configuration. The intention is to modify them to provide a dual passenger/freight capability. A contract for this conversion was signed in October 2005.

The first aircraft will be completed in 2007 with the final aircraft completed in 2010.

Target
Delivered
  • The project milestones in 2005/06 are to:
    • have the modification programme engineering design phase completed and accepted
  • Contract documents were signed on 10 October 2005.
  • Preliminary Design Reviews have been undertaken with the final review scheduled for September 2006.
  • induct the first aircraft into the contractor's facility for modification.
  • Aircraft induction will be delayed until early 2007 owing to more extensive design effort required and longer lead times in some items of equipment.
Financial summary of project costs charged to non-departmental appropriations as at 30 June 2006 (GST inclusive)
 
$
 
Project approval 220,603,771  
Foreign exchange variances to date and forecast to complete 316,721  
GST 27,575,375  
Total approved cost 248,495,867  
GST exclusive    
Expenditure to 30 June 2005 108,470,231  
Expenditure 2005/06 35,127,622  
Future commitments and forecasts 77,322,029  
  220,919,882  
GST    
GST to 30 June 2005 13,055,092  
Expenditure 2005/06 45,449  
Future commitments and forecasts 14,474,834  
  27,575,375  
Total forecast cost to complete 248,495,257  

Top | Previous | Next

Page contents Accessibility (list of Access Keys) Sitemap Homepage About us Defence Policy Acquisition Activities Reports & Publications Links Contact Us Search box New Zealand Government websites homepage